Standard Terms and Conditions
1. INSTALLATION WORK:
a) All electrical installation work will comply with BS7671: 2008 Amd 1 and any amendments in force at the time of the works.
b) All electrical installation work will comply with applicable Building Regulations in force at the time of the works.
c) Where work is to extend or modify existing circuits, costs quoted assume that the existing installation is in adequate condition and complies with minimum current regulations. Any works found required to bring the necessary parts of the existing installation up to standard will be at additional cost.
d) Unless stated otherwise, all cables will be concealed by chasing into the building fabric or concealed in building voids, under floors, etc. Where impracticable, cabling will be neatly surface run, either clipping direct or housed in trunking / conduit.
e) Where carpet or flooring coverings may require lifting to allow concealed installation work, no charge is made for this service, with best endeavours being made to avoid damaging them and to refit them to an acceptable standard. However, consideration of employing a specialist fitter may be prudent, at your cost to effect a fully satisfactory reinstatement.
f) Where agreed before hand and extra charge, chases to walls, etc will be re-filled to 2mm below plaster finish depth, however final finishing of skim coat plaster and final decoration is excluded.
g) All endeavours will be made to undertake installation work to a clean standard, using dustsheets and vacuum cleaning equipment as necessary. However, dust is inevitable. Where agreed before hand and at extra charge, we can provide a cleaning service.
h) The contract / quote outlines the expected duration of the installation work.
i) Whilst undertaking the installation work at the property, the client is required to provide water and power free of charge.
j) For property rewires the property must not be inhabited without prior agreement.
2. EXCLUSIONS:
a) Clearing and / or moving of furniture and other items blocking access to work areas are not included.
b) Except where detailed, builders work (creating of holes larger than 50mm diameter, creating of support structures, etc) are not included, except as outlined in 1d, e and f above.
c) Re-decoration and final making good is excluded from quoted costs, unless specifically detailed as included.
d) Removal from site and disposal of rubble, fittings, wiring, materials, general waste and packaging is not included. However, this can be provided at extra cost.
3. EXTRAS AND VARIATIONS:
a) All extras and variations must be agreed in writing prior to commencement.
4. PRICING:
a) The costs quoted assume continuous and unhindered access to the site by prior arrangement with you.
b) the customer continues to grant and facilitate the agreed and necessary access to the premises being worked on if the originally stipulated duration of the contracted works is to remain valid. Unless stated otherwise, the standard working hours between the hours of 09:00 hrs – 17:00 hrs Monday to Friday inclusive. Access may be required outside these hours to complete works on time as set out in the contract thus access may be required from 08:00 hrs – 20:00 hrs.
c) Any additional work not covered in our quoted costs will attract additional time charge rate of £35.00 per hour plus materials cost.
d) All figures quoted for materials are subject to VAT at the prevailing rate.
e) All figures quoted are valid for a date of 30 days from the date of the estimate or quotation.
f) You have a cooling off period of 7 days from accepting a quote from us or the length of time to the commencement of works if less than 7 days. Greater than 7 days could lead to a cancellation fee.
5. DEVIATIONS FROM BUILDING REGULATIONS AND BS7671:M
a) All work where applicable, will be executed fully in compliance with applicable Building Regulations and BS7671 in force at the time of the work, particularly in respect of work in dwellings to allow the legal Part P obligations to be met. Where a deviation from such regulations, a written instruction and record will be required.
6. RISK AND TITLE OF GOODS AND PROPERTY:
a) The risk in all goods supplied shall pass to the Client upon delivery.
b) All goods supplied shall remain the property of AIM Installations until all sums due have been paid in full.
c) The client is responsible for ensuring that the property is insured for the duration of the installation work.
7. WARRANTEE:
a) AIM Installations warrants its installation work to be defect free for a period of twelve months from invoice date. Such cover does not extend to goods not supplied by AIM Installations, physical damage to products, or any instance where the original installation has been altered or tampered with subsequently by third parties.
8. PAYMENT:
a) Unless agreed in writing payment in full must be made on completion of the specified works to AIM Installations.
b) Stage payments will be requested by prior arrangement where planned works take longer than 21 days or are over £3500. We reserve the right to request from you stage payments in the instance where works take longer than 21 days.
9. DISPUTE RESOLUTION:
a) In the event of a dispute, mediation is to be the preferred method of resolution.
b) Payment for full contract amount to be paid within 5 working days of completion regardless of any unresolved disputes, otherwise subject to 8%APR until paid in full.
c) Where we use sub-contractors to complete tasks out of our description (Joinery & Electrical) we do so in good faith. However, any problems that require a resolution will need to be done so with them directly. We do not guarantee the work of others.
d) In the unlikely event of a complaint, any remedial works will be undertaken by AIM Installations employees or selected sub contractors. We do not pay for others to complete such tasks.
10. PHOTOGRAPHS:
a) We reserve the right to take photographs and video of completed works for our records and for use in our portfolio unless requested in writing prior to commencement not to.